Tuesday, May 31, 2011

Where Should the Sediment Go? The Devil's Gate Dam Dilemma

UPDATE 8/2/2011: The Pasadena City Council unanimously approves use of Johnson Field for sediment storage during LA County's interim project to remove sediment buildup behind Devil's Gate Dam.

-------------------------------------

To understand the current dynamics playing out in the Hahamongna about sediment removal behind Devil's Gate Dam, we must look at what got us to this point.

Here's a short recap:

.The 2009 Station Fire wildfire burns almost 70% of the upper Arroyo Seco watershed, depositing over 1,000,000 cubic yards of sediment into the Hahamongna Basin, much of which collects behind Devil's Date Dam
.LA County plans to remove all sediment in the Basin under 'emergency' maintenance procedures which do not require an Environmental Impact Report
.The local environmental community protests and the LA County Board of Supervisors approves a resolution requiring a complete EIR be done before sediment removal occurs, with the exception that County Public Works can remove 25,000 cubic yards this summer directly behind the Dam because of emergency maintenance conditions.
.LA County Dept of Public Works finalizes its interim sediment measures and starts conducting community outreach meetings to review truck transportation routes to haul the sediment out of the Basin for relocation to Scholl Canyon.
.The interim sediment removal plan must be completed by October 15, 2011, when the annual rainy season traditionally begins.

Yet the controversy seems to go on....

Why?

First, while LA County has put together a generally sound interim sediment plan, it has failed in its ability to properly communicate this plan to the public. Case in point: last Thursday night's outreach meeting at La Canada High School to discuss the 'truck haul' plans. What didn't go wrong?  The powerpoint did not work. There were no handouts. A new alternative #4 to keep the sediment in the Basin was announced with little context as to why this option was now being offered. Presenters seemed to be at a loss to directly answer many questions posed by the attendees.

But the enviro community and residents are not blameless here, either. Numerous bloggers, local residents and environmental organizations continue to disseminate skewed information and promote 20th Century style scare tactics online and in whisper campaigns to rally their troops towards either stopping this sediment removal or warning of 'dire' consequences if it occurs. They aren't offering any proactive alternative solutions, either.

So let's look at the facts relevant to public safety. (All these documents are online and available to the public at the dpw.lacounty.gov site.)

If you click on the header to this blog, you will be taken to the  LA County Staff Report to the Board of Supervisors which accurately discusses the issues. Then take a look at the powerpoint for the interim removal plan here:

tp://dpw.lacounty.gov/wrd/removal/DevilGate/CVAC_Interim_Measures_20110525.pdf

When we cut to the chase these facts remain:

1. The sediment directly behind Devil's Gate Dam has reached a level of 1,009 feet
2. This sediment is blocking at least two sluice gates, which are responsible for releasing water through the flood gates.
3. This sediment is also close to clogging the outlet valves at the top of these sluice gates.
4. This sediment, if not removed this summer, will likely clog outlet valves, including tunnel water outlets after the next rainy season.

Clogged sluice gates and tunnel water outlets mean that the Watermaster will be unable to discharge water through the dam.

Here's the unknown: how much precipitation the Arroyo Seco watershed will get this rainy season. It's especially difficult to predict because we are now experiencing chaotic weather patterns, witnessed by Mississippi River flooding, deadly Southern tornados and a West Texas drought and fire storm. As one local example, the experts at NOAA predicted a 'dry' La Nina last year and we got instead one of the wettest seasons in recent years. Should we have another wet rainy season, even more sediment will flow into the Hahamongna, resting behind the Dam.

Based upon these facts, can we really afford to take the risk of doing nothing about sediment removal behind the Dam this summer?

Let's review the sediment removal 'haul out' options (see the map on the powerpoint link). Unfortunately, projects of this scope and type always have short-term negative impacts on the local community. Truck traffic with attendant noise over the 4 week haul out time period will inevitably be a short term nuisance to affected residents and local commuters (JPL, La Canada High students, park users).

It's totally understandable that residents are concerned about the County's initial preference to use Alternative Route #1 down Windsor Boulevard. For the County, it is the fastest route out and will require the minimal infrastructure work to get this job done. For years, these residents have dealt with the noise and congestion of heavy trucking on this roadway due to the La Vina development, the City of Pasadena's water treatment plant construction, and regular deliveries to JPL.

That's why the recent agreement between the County and the City of Pasadena Water and Power which makes the availability of Johnson Field, located on the northeast side within the Hahagmongna Basin, as a sediment removal holding site welcome news. Use of Johnson Field will decrease truck hauling by 80% since only 20% of the organic materials will have to be hauled out of the Basin itself. The remainder will be hauled to and 'stored' on Johnson Field, which has not been used as a playing field for years.

The local in-basin haul to Johnson Field will also support the short timeline the County has to move this buildup because sediment needs to be 'dried out' first before it can be relocated due of its heavy weight when saturated by water.

Ultimately, there is no solution that will make everyone 100% happy, so it's important to keep our focus on the big picture. The Hahamongna is first and foremost a flood control basin and water conservation reservoir. We continue to face dire long-term local water reliability challenges. Unfortunately, this past winter's extremely wet season has blunted our awareness that we still need to conserve water. All three of Southern California's imported water sources remain in distress. Beyond immediate public safety concerns, sediment buildup behind Devil's Gate Dam significantly reduces the amount of groundwater that can be stored for local recharge in the Hahamongna Basin.

All rivers carry both water and sediment. There is ample opportunity for all of us to work towards a fully integrated long-term strategy for sediment removal as part of the full sediment removal plan and EIR for the Hahamongna. In the meantime, let's support the interim sediment removal measures, including Johnson field Alternative #4 transport, so that our focus can be on proactive solutions for the future rather than on emergency disaster cleanup and a real risk to public safety.

Tuesday, May 24, 2011

Jacarandas on Parade

Spring in Southern California truly arrives when the stately jacaranda trees come into full bloom.

This array of flower splendor is no more evident than along a mile long arbor on Del Mar Boulevard in Pasadena, California. Pasadena may be the 'Rose City,' but in May of each year, it arrays itself in purplish blue flowers.

A South American native tree purportedly first imported by early leaders of the Los Angeles Arboretum to test flowering trees that could adapt to Southern California's climate, the jacarandas are found throughout the Los Angeles area and provide welcome bursts of color that announce spring has arrived.

As a transplant to Southern California myself, I quickly developed a strong affinity for the jacaranda, since my favorite flower is the purple lilac, which does not grow well in this climate. Yet every spring I can count on two weeks of purple color bursts, thanks to the majestic jacaranda tree.

Yes, I know it's not a native tree. Yes, I know that its flowers create a big mess when they drop.

But I don't care because more than any other plant or tree, the jacaranda truly announces that spring has arrived. And to see them at their best, there is no better place than along Del Mar Boulevard between Lake Avenue and the Arroyo Seco Parkway. Not a Pasadenan? Hop on the Gold Line, get off at the Del Mar station, and walk/bicycle a few short blocks to see these beauties. Hurry...take that stroll or drive before the flower show is over.

Saturday, May 14, 2011

Arroyo Property of the Week - Highland Park View Home

There's a phrase real estate agents use from time to time with their buyers. It goes something like this: Don't curb appraise the house when you drive by.

This sweet Highland Park view home built in 1911 is a great example of this adage. The exterior of this home is well-maintained but nothing to get excited about, which is why I haven't posted a photo here.

But once you get inside, it's a charming bungalow with upgraded  kitchen with granite countertops, a bonus room, and flat, useable backyard.

Did I mention that this 1128 sq foot 2 bedroom, 1 bath home on a 5620 sq ft lot is located just south of Yosemite Drive and can be yours for $375,000?

A large front porch to enjoy those views, hardwood floors, full bath with tub, detached garage and a 100 sq ft studio at the rear of the property enhance this cozy home.

In addition, the steps up to the front door are lined with Arroyo rock from my beloved Arroyo Seco stream, which was commonly used in homes built just after the turn of the 20th Century.

Best of all, this is a standard sale - no lenders, REO departments or lawyers to deal with - just nice sellers who are looking for the right buyer.

Interested? This gem is shown by appointment only, so give me a call at 323-230-9749 and I'll be happy to arrange a showing.

Monday, May 9, 2011

The Real Hahamongna Dilemma

At first glance, you may think this photo is the Arroyo Seco flowing through the Hahamongna.

But this is actually the Arroyo Seco flowing south of Devil's Gate Dam just above Brookside Golf Course and look at that sediment!

One of the saddest legacies of the devastating 2009 Station Fire is that the complete burn of the upper Arroyo Seco Watershed created massive sediment debris flows into the central and lower reaches.

While lots of public outcry is being played out in the media about LA County's plan to remove sediment in the Hahamonga and the impact of that operation on habitat in that basin, no one is talking about what will happen downstream if the dam fails due to sediment buildup overload.

Already, heavy sediment flows into the Central Arroyo Seco have damaged most river restoration enhancements completed in 2008, including complete mortality for the small, yet growing school of native Arroyo Chub fish that was successfully reintroduced. In fact, the backwater pool under the Colorado Street Bridge is so full of sediment, you wouldn't even know that a pool once existed there.

In addition to the habitat damage, the sediment buildup both above and below the Rose Bowl complex is such that, without sediment removal behind the Dam, this popular recreation area could experience a flood or near flood event within the next year or so if rainy seasons replicate last year's deluge. Moreover, LA County's effort to relieve stress on Devil's Gate Dam from sediment buildup has included extra water releases into the Central Arroyo, contributing to the sediment buildup there.

This flooding potentiality was driven home last week during a tour by flood program representatives of the California Department of Water Resources who expressed shock (their actual word) at the level of sediment buildup behind the dam and its growing buildup in the Central Arroyo, especially as it 'backs up' into the channelized area just before the softbed section south of the Parking Lot I picnic area.

What would it mean to Pasadenans and their neighbors if the Brookside Golf Course and the Rose Bowl areas flooded?

First, it would mean no access to highly used recreational amenities, including the Rose Bowl Loop, which draw almost 3,000,0000 people to Brookside Park every year. Secondly, it would mean a major financial and logistics emergency preparedness cleanup effort by the City of Pasadena and LA County which would cost in the tens of thousands of dollars at a time of stressed public agency funding. Finally, it would mean a direct loss of over $4,000,000 in annual revenues that the City of Pasadena relies upon to fund its operating budget.

Here are some sobering facts:

.the 1938 Arroyo Seco flood damaged 85% of Brookside Golf Course and filled the Rose Bowl to its first tier level of seating until the river changed course and spared further damage to the stadium
.the Arroyo Seco Concrete Channel is nearing the end of its useful life
.the lack of federal funding match to complete the US Army Corps of Engineers Arroyo Seco Feasibility Study, first approved in 2003, hampers federal financial support for channel realignment or relocation in the Central Arroyo
.there is a high risk of little federal support in the event of a flood event in Brookside Park because, in part, the Federal Emergency Management Agency (FEMA) never created a flood inundation map for the area after the Arroyo Seco was channelized
.the Arroyo Seco Concrete Channel has never really been challenged with the type of heavy water/sediment flow now possible, so it is unknown whether it will actually 'hold' should a catastrophic spring flood event like the current Ohio and Mississippi River flooding test its strength

Let's hope that the newly created Sediment Removal Advisory Commitee will work with LA County Flood Control Management District leadership, state agencies, and federal officials to find sustainable solutions to Arroyo Seco sediment buildup that takes into account the larger context of impact that goes beyond the mere perimeter of the Hahamongna Basin.